Process Related Products
|
Process Related Product Case Histories
Case History Report:
CHS20070911-0002
|
442 seal with SC/SC
Equipment: Other
Fan Pump
|
|
Problem: Heavy maintenance and sleeve wear. Previously installed packing would last 2-4 months with sleeve replacement required every 1- 1.5 years.
|
Case History Report:
CHS20070524-0006
|
442 Split Seal in Pulp and Paper
Equipment: Other
Fan Pump
|
|
Problem: Heavy maintenance and sleeve wear. Previously installed Mechanical Packing was lasting 2-4 months, with sleeve replacement every 1- 1.5 years.
|
Case History Report:
CHS20071001-0004
|
Pulp & Paper Industry - stock preperation
|
|
Problem: Problems were leakage into gear box, oil contamination, and poor reliability.
|
Case History Report:
CHS20071009-0001
|
221 Split Seal on Bottom Entry Pulper
Equipment: BELOIT
5 TON BOTTOM ENTRY PULPER
|
|
Problem: Previous meantime between failure with mechanical packing was 4 months. Problems included leakage into gear box, oil contamination, and poor reliability.
|
Case History Report:
CHS20071008-0003
|
Pulp & Paper Stock Preparation
Equipment: DIP
Pulper
|
|
Problem: Meantime between failure was 3 months with the previously installed packing . The customer reported problems with leakage into gear box and bearings, oil contamination and poor reliability.
|
Case History Report:
CHS20070919-0001
|
Hydropulper
Equipment: Other
HYDROPULPER
|
|
Problem: Previous meantime between failure was 4 months. Leakage into gear box, oil contamination, and poor reliability.
|
|
|