Wastewater Industry
|
Most Recent 5 Wastewater Related Case Histories [Click here for more]
Case History Report:
CHS20070918-0007
|
Wastewater pumping station
Equipment: OTHER
HORIZONTAL SPLIT CASE
|
|
Problem: Meantime between failure was 1 year. The problem was installation.
|
Case History Report:
CHS20070920-0003
|
Sludge processing
Equipment: Other
Positive displacement screw pump
|
|
Problem: New installation was needed.
|
Case History Report:
CHS20070924-0001
|
Singles stage vertical pump
Equipment: Other
Singles Stage Vertical Pump
|
|
Problem: Previous meantime between failure was 6 months, sleeves were 2 years.
Problems encountered were leakage and housekeeping.
|
Case History Report:
CHS20070927-0002
|
Wastewater pumping station
Equipment: Other
Axial Flow Centrifugal Pump
|
|
Problem: Previous meantime between failure was 1 year.
Shaft Sleeve almost cut through after one year. Also expensive rump overhaul along with leaking.
|
Case History Report:
CHS20070912-0001
|
Sump Pump Lifting Station
Equipment: DEG
4501, 4511,4521 VERT SUMP PUMP
|
|
Problem: The previously installed mean time between failure was every 1 to 2 years and meantime between failure for sleeves was every 3 to 4 years. Heavy leakage from time to time and therefore risk of sump overflow.
|
|
|